BIRMINGHAM

DEMOLITION PROJECT: BIRMINGHAM - COLMORE GATE

PROJECT OVERVIEW

Strip out, 10 office floors and 4 double shop floor units. Working with the tennants and building users in a live environment to minimise disruption.

Full package comprising of:

  • Carry out pre demolition surveys
  • Application of Section 81
  • Risk assessment
  • Planning, including 3d phased method statements
  • To carry out full soft strip



SUSTAINABILITY STATISTICS

  • 100% of wood recycled
  • 80% of construction & demolition waste (due to fridge panels being non-recyclable)
  • 100% 110 tonne, metal
  • 80% total all materials recycled



KEY ACHIEVEMENTS

  • Working safely at height
  • Working and liaising with local residence to avoid disruption
  • Safely and securely removing contamination
  • Detailed Traffic management plan put into place to minimize disruption to local infrastructure
  • Local authority Deadline requirement
  • Working under Covid 19 restrictions to protect the safety of visitors and Charlton group staff

  • Category
  • ClientAshtrom Property UK
  • StartNovember 23, 2021
  • EndFebruary 23, 2022