Farnborough

DEMOLITION PROJECT: FARNBOROUGH - TECHNICAL COLLEGE

PROJECT OVERVIEW

Full demolition and recycling of former teaching block.

Full package comprising of:

  • Carry out pre demolition surveys
  • Application of Section 81
  • Risk assessment
  • Planning, including 3d phased method statements
  • To carry out full soft strip
  • Full scaffolding
  • Full demolition
  • Reduce level excavation Cut & Carve
  • Asbestos removal



SUSTAINABILITY STATISTICS

  • 100% of wood recycled
  • 96% of construction & demolition waste 100% 1,500 tonne 6F5 material
  • 100% 75 tonne, metal
  • 96% total all materials recycled



KEY ACHIEVEMENTS

  • Working and liaising with local residence to avoid disruption, due to high volume high street location
  • Detailed Traffic management plan put into place to minimize disruption to local infrastructure
  • Local authority Deadline requirement
  • Working under Covid 19 restrictions to protect the safety of visitors and Charlton group staff

  • Category
  • ClientConcept
  • StartJuly 20, 2020
  • EndSeptember 29, 2020