FARNHAM

DEMOLITION PROJECT: FARNHAM

PROJECT OVERVIEW

Jacobson House was a former shop and studio located in a prime residential area of Surrey.

Our works on site consisted of:

  • Site setup and welfare
  • Arranging asbestos surveys and removal
  • Full protection scaffold with Monoflex
  • Full demolition/site clearance including lifting and removing foundations.
  • Crushing and stockpiling recycled 6F5 material for future use by our client.
Work was completed on time and to client satisfaction

ACHIEVEMENTS

  • Working and liaising with local residents to minimise disruption.
  • Complex site traffic management plan taking into account close proximity to local school and shops.
  • Working to the new COVID-19 restrictions to protect the safety of site visitors and CJ Charlton Group Ltd staff.

  • Category
  • ClientPrivate Client
  • StartNovember 01, 2020
  • EndNovember 30, 2020