Surrey

DEMOLITION PROJECT: SURREY

PROJECT OVERVIEW

Full demolition, recycle and earthworks on former equestrian centre.

Full package comprising of:

  • Carry out pre demolition surveys
  • Application of Section 81
  • Risk assessment
  • Planning, including 3d phased method statements
  • To carry out full soft strip
  • Full demolition
  • Crushing material on site
  • Pile mat installation
  • Reduce level excavation
  • Asbestos removal and contaminated ground remediation



SUSTAINABILITY STATISTICS

  • 100% of wood recycled
  • 99% of construction & demolition waste
  • 100% 900 tonne crushed 6F5 material – this was used on site for piling mat construction
  • 100% 52 tonne, metal
  • 99% total all materials recycled



KEY ACHIEVEMENTS

  • Working with high water table (flood plain) Working and liaising with local residence to avoid disruption
  • Detailed Traffic management plan put into place to minimize disruption to local infrastructure
  • Local authority Deadline requirement
  • Working under Covid 19 restrictions to protect the safety of visitors and Charlton group staff

  • Category
  • ClientLofthouse Residences
  • StartSeptember 15, 2020
  • EndJanuary 08, 2021